Troubadour - OPENING SUMMER 2027
-
Utility work began in November 2024 and completed in February 2025.
Vertical construction began in Spring 2025 and is scheduled be completed in Summer 2027.
-
The following traffic control plan was finalized in collaboration with the City of Lubbock. Both 14th Street and 15th Street will remain open to two-way traffic, though lanes will be narrowed due to construction fencing around the site for the foreseeable future.
———
Our construction team will soon begin installing the building’s exterior finish using EIFS (Exterior Insulation and Finish System). EIFS is a layered wall system used on many commercial and residential buildings. It insulates the building, improves energy efficiency, and gives the exterior a durable, stucco-like finish. Crews first attach rigid foam insulation boards to the building’s exterior walls. They then sand, or “rasp,” the boards to create a smooth, even surface. After that, they apply a base coat with reinforcing mesh and finish with a textured protective coat. During the rasping step, you may notice small, lightweight particles of white foam in the area. These particles are not hazardous, but we know they can be a nuisance, especially on windy Lubbock days. To keep the area as clean as possible, our general contractor, Teinert Construction, is installing netting around the scaffolding to catch debris. Crews will also run vacuums on the scaffolding and at ground level to collect foam as they work. We appreciate your patience during this phase.
———
We will continue to provide updates on the progress of the work and any changes in the plans.
-
Discover more about our local sponsorships in the "News" section below.
Current Site Progress
In the news