2413 14TH STREET LUBBOCK, TX OPENING SUMMER 2027
-
Utility work began in November 2024 and completed in February 2025.
Vertical construction began in Spring 2025 and is scheduled be completed in Summer 2027.
-
The following traffic control plan was finalized in collaboration with the City of Lubbock. Both 14th Street and 15th Street will remain open to two-way traffic, though lanes will be narrowed due to construction fencing around the site for the foreseeable future.
———
Upcoming concrete pours are currently planned to begin setup at the following dates and times: 9/10 at 3:00 AM. As with any early morning work, you may notice increased noise and temporary site lighting to ensure the safety of our crew.
———
The City of Lubbock, in collaboration with Parallel, has initiated a street speed study aimed at slowing traffic flow.
———
We will continue to provide updates on the progress of the work and any changes in the plans.
-
Discover more about our local sponsorships in the "News" section below.
Current Site Progress
In the news